Leegate: demolition is complete

London Square has confirmed that the demolition phase of the development is now complete and the demolition team is expected to be leaving the site by July 3rd. .

London Square is about to post a bulletin on its noticeboards confirming that the completed work includes :

  • the demolition of the former petrol station (later the car wash). The fuel tanks have been removed.
  • The removal of all asbestos on the site by a licenced asbestos contracator.
  • the demolition of the garages at the south end of the site where London Square plan to build a terrace of houses.

There is still some work to be done before the demolition contractors can leave. This includes the removal of surplus hardcore in eight wheel lorries.